I-205 Abernethy Bridge project hits major milestone, but with big cost overrun

By Kristian Foden-Vencil (OPB)
Nov. 25, 2026 2 p.m.

Work crews moved the northbound side of the Abernethy Bridge 7 feet south last weekend. Next month they’ll move the southbound side. The aim is to add new lanes and make sure the bridge can survive a subduction zone earthquake.

Work crews hit a major milestone this weekend in a multi-year Interstate 205 bridge replacement project.

THANKS TO OUR SPONSOR:

They lifted the northbound roadbed of the Abernethy Bridge, which connects Oregon City and West Linn, and they moved it 7 feet south.

Oregon Department of Transportation engineer Ian Cannon said it went well.

“There are two purposes to this project,” Cannon said. “One has been to widen the bridge so that in the future there’ll be room for an additional lane on 205. And the other purpose is to make it seismically resilient.”

Next month they’re scheduled to move the southbound side.

Since work started in 2022, crews have replaced all the main vertical support piers that held up the bridge, while traffic continued to flow on I-205.

“The new piers go down about 200 feet to bedrock,” said Cannon. “They’re designed to survive the Cascade Subduction earthquake.”

The wider piers allow the roadbeds to slide apart so crews can add new lanes.

THANKS TO OUR SPONSOR:

ODOT made an effort last weekend, with signs and social media alerts, to publicize that the northbound lanes of the bridge would be closed.

But a lot of drivers spent significant time driving around the closure to get across the Willamette River.

“There was quite a bit of traffic,” Cannon said. “I think that reflects the importance of this route.”

While the bridge move went well, the whole project is significantly over budget.

When ODOT awarded the initial contract in 2022, the expected cost was $495 million. But that has now risen to $697 million.

ODOT spokesperson David House said there are a number of reasons for the cost overruns.

“We went through a pandemic, and supply and personnel issues, and then historic inflation. Inflation we haven’t seen since the 1970s.”

Tolls for the bridge had also been authorized by the Oregon Legislature, but were later canceled.

The federal government built Abernethy Bridge in the 1960s. But maintenance now falls largely to the state.

The project is scheduled to be finished by fall 2027.